Segments 1 & 2
Segments 1 and 2 extend from Beltway 8 to IH-610, and from IH-610 to IH-10 respectively.

The Mayor’s public process for Segments 1 and 2 is being led by the Planning & Development Department with help from a Facilitation Group composed of community leaders and subject matter experts. This group is guiding the City in reviewing comments, identifying impacts, and working towards opportunities for incorporation into the project.


Process & Timeline
City staff and a team of experts from Huitt-Zollars and UH Community Design Resource Center will conduct a multi-stage process for identifying changes to the project, mitigation measures, and opportunities for improvements related to the project but that would be funded and led by other entities.

  • Now: Baseline Analysis
    Analyze impacts and comments already received

  • August 13, 15 & 17: First Community Workshops
    Present maps and diagrams and build consensus on goals

  • August-November: Investigate and Develop Alternatives
    Research and develop alternatives based on feedback received

  • December: Second Community Workshops
    Present and discuss alternatives, build consensus on recommendations

  • End of 2019: Publish Recommendations and deliver to Mayor Turner

The City’s team will engage TxDOT throughout this process to make sure they’re aware of what the community is saying and are evaluating the resulting alternatives. Outcomes of the process will be shared with Mayor Turner and his NHHIP Steering Committee.

Process Graphic


In June 2019, the City and TxDOT co-hosted two public meetings to provide an overview and status update of NHHIP, and to inform people about the City-led engagement process.

  • Thursday, June 20, 2019
    Harris County Department of Education Conference Center

  • Wednesday, June 26, 2019
    Acres Homes Multi-Service Center

Meeting Materials (both dates):